Before day one — the handoff requirements
Delivery should be able to reject a handoff that is missing any of these, with a reason. That single rule prevents most onboarding delay.
- Scope and deliverables exactly as sold, in writing, attached to the record.
- Anything promised verbally during the sale, captured explicitly.
- Named customer sponsor and day-to-day contact, with roles and contact details.
- Access, data and dependencies listed, each with a named owner on the customer side.
- Commercial terms relevant to delivery: start date, duration, agreed volumes.
- Known risks or constraints the sales owner is aware of.
The milestone spine
| Milestone | Owner | Target | Exit condition | On slip |
|---|---|---|---|---|
| Kickoff held | Delivery owner | Day 3 | Scope, contacts and success measure confirmed in writing | Escalate to the sales owner who sold it |
| Access and data ready | Customer sponsor with delivery support | Day 7 | Everything needed to deliver is in place and verified | Named blocker raised with the sponsor |
| First delivery | Delivery owner | Day 14 | Customer has received the first real output | Delivery lead reviews capacity and sequence |
| Customer-run success | Delivery owner | Day 30 | Customer performs the core task unaided | Health rating drops; account review triggered |
| Steady-state handover | Account owner | Day 45 | Ownership, cadence and open items transferred explicitly | Handover blocked until open items are assigned |
Per-milestone working checklist
- Milestone exists as a dated task or stage on the customer record, not in a private document.
- One named owner, not a team.
- Exit condition is verifiable by someone who was not in the meeting.
- Slip action names a person with the authority to act.
- Customer-side dependencies have customer-side owners and dates.
Handover document
- Delivered
- What was actually delivered against what was sold, with any variance noted.
- Open items
- Everything unfinished, each with an owner and a date. An empty list is the goal, not a formality.
- Ownership
- Who owns the relationship now, and who the customer contacts for what.
- Cadence
- The ongoing rhythm: reviews, reporting and checkpoints, with the first date already booked.
- Risk notes
- Anything the steady-state owner should watch, in plain language.
Related work
Design the process with the customer onboarding playbook; the failure it prevents is every customer gets a different onboarding.